Lebuhraya PLUS Sedenak-Kulai dan SDE Mungkin Dibuka Awal 2027
· Rumah Bumi Johor
Two widened highway stretches in Johor could open to traffic early in 2027, before all the works are finished. State works, transport and infrastructure committee chairman Mohamad Fazli Mohamad Salleh said on 13 Nov 2026 that talks with the highway operators, the Malaysian Highway Authority (LLM) and contractors are under way. For families living in Kulai, Sedenak, Simpang Renggam or the Kota Tinggi side of the Senai-Desaru Expressway, this affects the daily drive.
Quick answer: The 14.5km Sedenak-Kulai stretch of the North-South Highway could open in Feb or Mar 2027, and the 9.34km Senai-Desaru Expressway stretch from the Sungai Johor bridge to Sungai Semenchu in Jan or Feb 2027. These are early openings, so some works will continue after that.
Updated 19 Nov 2026. General information, not legal or financial advice.
The two stretches that may open early
| Stretch | Length | Possible early opening |
|---|---|---|
| North-South Highway (NSH), Sedenak to Kulai | 14.5km | Feb or Mar 2027 |
| Senai-Desaru Expressway (SDE), Sungai Johor bridge to Sungai Semenchu | 9.34km | Jan or Feb 2027 |
Fazli said the plan is to let traffic use the new lanes first, even though construction is not fully done. So expect the usual signs of a site for some months: lane shifts, lower speed limits and night works.
The full NSH widening plan
The Sedenak-Kulai stretch is one part of a bigger widening of the NSH in Johor. Here is how the phases stand, based on the same report:
- Phase One, Package A (Senai Utara to Sedenak, 21.8km): RM525 million. Work began in Jun 2024, completion targeted for Jun 2027. This stretch was put first because its hilly terrain slows heavy vehicles and causes jams.
- Phase One, Package B (Kulai to Senai Utara): began in Jun 2025, completion expected in Dec 2027.
- Phase Two (Sedenak to Simpang Renggam, 16.6km): RM365.22 million, 26.68% complete. Started 28 Jul 2025, scheduled to finish on 27 Jul 2028.
- Phase Three (Simpang Renggam to Machap, 14km): RM487 million. Work is expected to start this December and take about three years.
- Phase Four: the state will seek approval to widen further from Machap towards Ayer Hitam or Yong Peng.
The SDE upgrade on the eastern side
On the Senai-Desaru Expressway, the Sungai Johor bridge to Sungai Semenchu upgrade costs RM128.52 million and adds two lanes, giving four lanes in each direction. It is scheduled for completion in Apr 2027. Phase 2A, about 4.7km from Cahaya Baru to the Sungai Johor bridge, is estimated at RM117 million, with work expected to start towards the end of 2026 and finish by Dec 2029. The state will also seek approval for Phase 2B, the 10.9km from Sungai Semenchu to Penawar.
Looking at homes in Kulai, Sedenak or along the SDE?
Tell us where you work. We will suggest areas that fit your daily drive, now and after the widening.
What this means for home buyers
Highway works matter most to people who drive the same stretch twice a day. If you work in Johor Bahru or the Senai area and live further north, the Sedenak-Kulai jam is part of your day. An early opening of the new lanes could shorten that, but the full benefit only comes when each package is finished.
- Kulai and Sedenak: new industrial parks and data centres are bringing jobs to this side. See our guide to Sedenak and Bukit Batu for what is there today.
- Simpang Renggam: Phase Two only finishes in Jul 2028. If you commute from here, plan for works on the route for some time. Read our Simpang Renggam area guide.
- Kota Tinggi and Bandar Penawar: the SDE upgrades help the road towards Desaru, though Phase 2B still needs approval. See our Kota Tinggi and Bandar Penawar guide.
One caution: a developer brochure may say a project is close to a highway upgrade. Check which package that is, and its own completion date, before you count it as a reason to buy. Timelines for road works can move, and a target is not a promise.
Want us to compare two areas for you?
Send the two areas and your workplace. We reply with the road works on each route and the homes we list nearby.
Common questions
When will the Sedenak-Kulai widening open?
The state hopes to open the 14.5km stretch in Feb or Mar 2027. Package A as a whole is targeted for Jun 2027.
Is the whole road finished when it opens?
No. Fazli said the routes would open first even though construction is not fully complete.
How many lanes will the SDE have near the Sungai Johor bridge?
Four lanes in each direction after the RM128.52 million upgrade, due in Apr 2027.
Will the widening go beyond Machap?
The state will seek approval for a Phase Four from Machap towards Ayer Hitam or Yong Peng. Nothing has been approved yet in the report.
Sources: The Star, 13 Nov 2026, Two highway stretches in Johor may open early. Cover photo: Muhammad Faiz Zulkeflee, Unsplash.