Whether you are building a new house on your own lot or adding a big extension, the council has to approve it before work starts. In Johor this runs through each council’s One Stop Centre (OSC). This guide explains the two approvals most owners meet, planning permission and building plan approval, the documents councils ask for, and what happens if you build without them.

Updated 19 Nov 2026. General information, not legal or financial advice.

Quick answer: Your architect or engineer, acting as the principal submitting person (PSP), submits planning permission under the Town and Country Planning Act 1976 where required, then the building plans under the Street, Drainage and Building Act 1974, online through OSC 3.0 Plus. You supply the title, quit rent and assessment receipts and your IC. Work without approval can be demolished after a 30-day notice.

Two approvals, two laws

Approval Law What it decides
Planning permission (kebenaran merancang, KM) Town and Country Planning Act 1976 (Act 172), application on Form A under section 21(1) Whether the use, density and layout fit the local plan
Building plan approval Street, Drainage and Building Act 1974 (Act 133) and the Uniform Building By-Laws Whether the design, structure and fire safety meet the by-laws
Sources: MBJB planning permission checklist 2025; Majlis Daerah Tangkak building plan checklist; Berita RTM, 12 Feb 2026.

Small renovations inside an existing house follow a lighter route through a renovation permit. That is covered in our guide to MBJB renovation permits. This article is about new houses and larger works.

Who submits the plans

You do not submit the drawings yourself. Plans must be prepared and signed by a qualified consultant, who acts as the principal submitting person (PSP). Councils ask for your letter appointing the consultant and the PSP’s letter of authority. The PSP stays responsible until the end, when they certify the house for the Certificate of Completion and Compliance (CCC).

Documents councils ask for

Each council has its own checklist, but the core items repeat. These come from MBJB’s 2025 planning permission checklist and the building plan checklist of Majlis Daerah Tangkak:

  • Form A signed by the owner, with name, address and IC number, plus a copy of the IC.
  • A copy of the land title. MBJB asks for a title print issued within one year; Tangkak accepts proof of ownership dated within six months.
  • The latest quit rent and assessment tax receipts.
  • Consent of the bank if the land is charged, and consent of every co-owner.
  • Site plan, location plan, floor plans, sections and elevations, signed by the consultant.
  • A fire requirements plan for the Fire and Rescue Department, and current photos of the site.
  • The planning permission letter, if one was needed, and the fee receipts.

Planning to build or extend?

Tell us the council area and what you plan. We will share the checks that matter most.

Fees and how to apply

Everything is uploaded as PDF to OSC 3.0 Plus, and MBJB registers an application only once the hard copies are complete. For planning permission, MBJB’s fee table charges RM30 per unit for a detached house and RM20 per unit for low-cost or affordable homes, paid by FPX through PBTPay after the bill is generated. Building plan fees are calculated separately by floor area, so ask your PSP for the council’s figure.

  1. Appoint the PSP and agree the design.
  2. Submit planning permission through OSC, if your project needs it.
  3. Submit building plans with all agency plans attached.
  4. Receive approval, read the conditions and notify the start of work.
  5. Build, with the PSP certifying each stage, then obtain the CCC.

If you build without approval

Berita RTM reported on 12 Feb 2026 that councils can demolish development carried out without planning permission, under section 70 of Act 133 and sections 19 and 21 of Act 172, after issuing a 30-day notice and following set procedures. There are practical costs too: banks will not release a construction loan without approved plans, and a house without a CCC is harder to sell or refinance. Learn more about the CCC and how a full self-build fits together in buying a lot and building your own house.

Rather buy a house with a CCC already?

We list completed and upcoming projects in Johor. Tell us your budget.

Common questions

Do I always need planning permission to build one house?

It depends on the land, the project and the local plan. Ask your PSP to confirm with the council planning unit before you finalise the design.

Can I draw and submit the plans myself?

No. The plans must be signed by a licensed consultant acting as the PSP, and the council deals with the PSP.

How much is the planning permission fee at MBJB?

RM30 per unit for a detached house and RM20 per unit for low-cost or affordable housing, per MBJB’s 2025 checklist. Building plan fees are separate.

What happens if the council finds unapproved works?

The council can issue notices and, after a 30-day notice, demolish development done without permission, following the set procedure.

Sources: MBJB planning permission checklist 2025; Majlis Daerah Tangkak building plan checklist (Jan 2024); Berita RTM, 12 Feb 2026; NextSix on PSP and CCC (Nov 2025). General information, not legal or financial advice. Cover photo: K O, Unsplash.

Satu respons kepada “Kelulusan Pelan Bangunan Rumah di Johor: Kebenaran Merancang dan OSC”

  1. […] Permohonan dibuat melalui Pusat Setempat (OSC) majlis dalam sistem OSC 3.0 Plus. Jika perlu, anda dapatkan kebenaran merancang dulu, kemudian kelulusan pelan bangunan, dan selepas itu kebenaran memulakan kerja. Baca syarat dalam surat kelulusan sebelum kontraktor masuk ke tapak. Proses penuh majlis ada dalam panduan kami tentang kelulusan pelan bangunan di Johor. […]

Tinggalkan Balasan