Jade Palace Danga Bay: Pengajaran Projek Lewat Siap di Johor Bahru

· Rumah Bumi Johor

Several cranes above buildings under construction

Jade Palace was meant to be finished by the end of 2018. That date is long gone. The project is a large freehold development on the Danga Bay waterfront in Johor Bahru, launched in 2015 by the Chinese developer Greenland. Here is what the public record shows, and what any buyer should check, however the project ends.

The facts on record

  • Developer: Greenland Danga Bay Sdn Bhd, the Malaysian arm of Greenland Group of China.
  • Tenure: freehold.
  • Size: PropertyGuru lists about 2,200 homes in 13 towers. (PropertyGuru)
  • Timeline: launched in 2015, with completion then targeted for end 2018. As that date has passed, check the SPA delivery date for each tower.
  • Status: public sources do not give a clear status for each tower. Ask for the latest progress report and visit the site.
  • Other plans: on 29 Nov 2023, MB World Group signed a development rights agreement with Danga Jed Development Malaysia, a Greenland Group unit, for a 17-acre mixed development at Danga Bay. It covers 2,930 serviced apartments and eight townhouses in three phases, with 2,003 units in phase 1. The reports do not mention Jade Palace, so we cannot say whether any Jade Palace tower is included. (NST, The Star)

Why buyers should care

The finances of the wider group are public. In May 2022, the Hong Kong unit of Greenland asked bondholders for one more year to repay a US$488 million offshore bond. (SCMP) That does not prove what happened to any one tower in Malaysia. It does show why you should check who is going to finish the job.

Lessons for buyers

  • A parent company in trouble can slow a project. When the group runs short of cash, building work and sales can stop.
  • A rights deal is not a finished building. A new party taking development rights does not mean your unit will arrive on time.
  • Mixed progress is hard to read. When finished towers stand beside stalled ones, it is hard to judge progress from outside.
  • Old dates mean nothing. Older launch material often shows a completion date that has already passed.

5 checks before you buy any Johor project

  1. Who finishes the work? Find out the current developer, any rights agreements, and who is legally responsible for delivery.
  2. Is construction moving? Ask for the latest progress report and the name of the main contractor, then visit the site yourself.
  3. What does the SPA promise? Check the delivery date, any extension, and the liquidated ascertained damages (LAD) you can claim if the date is missed.
  4. Is the permit valid? Ask for the advertising permit (APDL) number and when it expires.
  5. Is there a Bumi lot for you? In new projects with Bumi lots, Bumiputera buyers get a Bumi SPA price 15% lower than the non-Bumi price. Ask before you commit, and civil servants should also ask whether LPPSA financing is accepted.

JB projects that tick more of these boxes

These are not substitutes for Jade Palace. Each one still needs its own checks before you buy.

Freehold · Completed

R&F Princess Cove Phase 2

A finished freehold project in JB City Centre. There is no construction risk left.

Ask us: how the building is run and its fee record.

View projectAsk price

Freehold · Under construction

Causewayz Square @ JBCC (EXSIM)

Freehold serviced apartments with a retail podium on Jalan Lumba Kuda, Bukit Chagar. Under construction, with completion targeted for Dec 2030.

Ask us: who manages the retail lots, and the completion date in the SPA.

View projectAsk price

Freehold · Under construction

R&F Princess Cove Phase 3 (New Casa Suites)

A freehold project in JB City Centre, under construction, with completion targeted for 2028.

Ask us: the latest progress and the SPA delivery date.

View projectAsk price

Freehold · New launch

Hillview @ Senibong Cove (WM Senibong)

A new launch within Senibong Cove, with Tower 1 targeted for Mar 2029.

Ask us: whether there are Bumi lots for the unit type you want.

View projectAsk price

Leasehold · Under construction

The Asteriaz @ Kebun Teh (EXSIM)

A leasehold project in the Larkin area, under construction, with completion around 2029.

Ask us: the lease terms and whether Bumi lots are available.

View projectAsk price

Leasehold · New launch

The Celestz @ Kebun Teh (EXSIM)

A leasehold new launch in the Larkin area. Completion is set at 52 months from the APDL date.

Ask us: the APDL date and whether Bumi lots are available.

View projectAsk price

Want us to check a project for you?

Send us the project name. We will look at the developer, progress and SPA points with you.

Common questions

Is a development rights agreement the same as a sale?

No. It means another party has agreed to develop the land. Ask who is legally responsible for finishing the work and handing over your unit.

What is LAD?

Liquidated ascertained damages are the compensation written into the SPA if the developer misses the delivery date. Check how much it is and how it is paid.

Should I avoid stalled projects?

Not always. A stalled project needs a clear plan to finish, a confirmed contractor, and an SPA you have read carefully before you commit.

Updated 16 Nov 2026. Sources: PropertyGuru, The Star, SCMP. Cover photo: EJ Yao, Unsplash.

Tinggalkan Balasan

Alamat e-mel anda tidak akan disiarkan. Medan diperlukan ditanda dengan *

Shortlist for my budgetAsk about this