Pemaju Lewat Serah Rumah di Malaysia: Hak LAD dan Tuntutan Tribunal

· Rumah Bumi Johor

Person signing paperwork at a desk

When a developer hands over a home late in Malaysia, the Housing Development (Control and Licensing) Regulations 1989 apply. Under the standard agreement, a strata buyer (Schedule H) should get vacant possession within 36 months of signing. A developer who misses that date owes liquidated damages (LAD) of 10% a year of the purchase price, counted daily from the deadline until you take possession. This is not legal advice; ask your lawyer.

Updated 16 Nov 2026.

Worried about a handover date?

Tell us the project. Before you sign, we will show you where the date sits in the agreement.

How long does a developer have to hand over?

Licensed developers must use the contract form set by the Minister (Housing Development (Control and Licensing) Act 1966, section 24). In the standard forms, the handover period depends on the property type:

  • Schedule G (land and building, such as landed houses): vacant possession within 24 calendar months of the agreement date.
  • Schedule H (a building or land to be subdivided into parcels, such as condos and serviced apartments sold as strata): vacant possession within 36 calendar months of the agreement date.

Both schedules were replaced by the Regulations from 1 Dec 2007. We took the 24-month and 36-month periods from the published schedule text and from law-firm summaries. We could not open the current gazette copy of the schedules ourselves, so confirm the periods in your own agreement and with your lawyer.

LAD explained

LAD stands for liquidated ascertained damages: a fixed rate for late delivery that the agreement sets in advance. In the standard schedule, the developer pays 10% per annum of the purchase price, calculated day by day from the end of the handover period until the buyer takes vacant possession.

Here is how the formula works, not what anyone will get: for a RM600,000 purchase price, 10% a year is RM60,000 a year, or roughly RM164 a day. Whether LAD applies to you, and for how many days, depends on your agreement and the facts. Let a lawyer work it out.

CCC and CF: why they matter at handover

The CCC is the certificate of completion and compliance under the Street, Drainage and Building Act 1974. The Act, as amended by Act A1289, replaced the older certificate of fitness for occupation (CF) with the CCC. The developer must send the CCC to the Controller of Housing within 21 days of getting it (section 7). The CCC date also starts a Tribunal time limit, explained below.

Your agreement sets out how vacant possession is delivered: the notice, the architect’s certificate and the approvals needed. Read that clause with your lawyer before the project is close to completion.

Claiming through the Tribunal for Homebuyer Claims (TTPR)

Part VI of the 1966 Act sets up the Tribunal, which KPKT runs. As written in the Act:

  • A homebuyer may file a claim (section 16L). Someone who later buys from the first purchaser also counts as a homebuyer (section 16A).
  • Each claim is capped at RM50,000 (section 16M, where Act A1289 replaced ‘twenty-five’ with ‘fifty’). A plan to raise it to RM250,000 was reported in Apr 2024; we found no sign it has become law.
  • The claim must arise from the sale and purchase agreement and be filed within 12 months of the CCC date, the end of the defects liability period, or the date the agreement was terminated (section 16N(2)).
  • You cannot split one matter against the same party to stay under the cap (section 16Q), and a claim within the Tribunal’s power cannot also go to court between the same parties (section 16R, 2006 reprint). The Federal Court held that the RM50,000 cap applies per claim, not to all claims on one property (EdgeProp, 22 May 2023). Awards are final and binding (section 16AC).
  • The Tribunal must decide without delay and, where practicable, within 60 days of the first hearing day (section 16Y).

Claims above the cap, court action and time limits (section 6 of the Limitation Act 1953 sets six years for actions based on a contract) raise legal questions about when time starts to run. Ask your lawyer. We do not predict how any claim will end.

Late, or abandoned? Can you end the agreement?

The law treats stopped work differently from a late handover. Under section 8A (as replaced by Act A1415, 2012), a buyer may end the agreement if work has stopped for six months or more. This needs the end financier’s consent and a certificate from the Controller, and a refund is due within 30 days. Section 18A makes abandoning a housing project an offence. If this sounds like your case, talk to your lawyer first.

Any changes to the law in 2024 to 2026?

We found no enacted change to the Schedule G and H periods, the 10% LAD rate or the RM50,000 Tribunal cap. KPKT has said it is amending Act 118 and drafting a new Real Property Development Act (RPDA) to replace it. In Jul 2026 the minister said the draft was at the final stage (Bernama, 31 Jul 2026). We have not seen it passed, so this guide covers the law as it stands in the sources below.

Before you sign a new-launch agreement

  • Handover period: is it 24 or 36 months, and from which date?
  • LAD clause: does it match the standard wording, and does it mention extensions or waivers?
  • CCC and vacant possession steps: who sends the notice, and what must come with it?
  • Any letter you are asked to sign later: read it with your lawyer first, especially if it talks about giving up rights.
  • Your Bumiputera options: in new projects with Bumi lots, Bumiputera buyers get a Bumi SPA price 15% lower than the non-Bumi price. Civil servants may use LPPSA, and first-home buyers may qualify for the stamp duty exemption. The handover rules above apply to Bumi lots in the same way.

Our property viewing checklist for Johor Bahru lists what to ask at the sales gallery. Related: the Housing Development Account, LAD and the Tribunal, and Johor abandoned housing projects.

Projects to compare, with the completion dates on our pages

The Housing Development Act sets the legal timetable for every licensed developer. The dates on these cards are what our project pages say, not the legal deadline; the deadline that binds is in your signed sale and purchase agreement. We show these projects only for the date information, and we make no comment on any developer’s delivery record.

Johor Bahru property

Aethera Residences

TenureFreehold, JB city centre
CompletionExpected 2030
Layouts1+1 bed to 4-bed duplex
AccessAbout 400 m to the RTS by covered walkway (proposed, not built)
Why it fits
Still being built, so the handover date in your agreement is the first thing to read. We can show you where it is.
Johor Bahru property

Gen Sphere

TenureFreehold, walk to CIQ and RTS
CompletionExpected Q4 2029
Layouts1 to 3 bed
AccessAbout 400 m on foot to the CIQ
Why it fits
A strata tower with a long build ahead, for buyers who want to understand the timetable before booking.
Johor Bahru property

Sky Curve @ Taman Perling

TenureFreehold serviced apartment
CompletionJun 2029 (developer disclosure; the SPA date binds)
Layouts1 to 3 bed
AccessAbout 13.3 km by road to RTS Bukit Chagar (measured)
Why it fits
Its page already separates the developer disclosure from the date in the sale agreement, which is the point of this guide.
Johor Bahru property

KSL Ceros Residences @ Nusa Idaman

TenureFreehold serviced apartment, Iskandar Puteri
CompletionQ4 2027
LayoutsStudio to 3 bed
AccessAbout 5 km to the Second Link Expressway; you would drive to the CIQ and RTS
Why it fits
The earliest completion date of the four, so buyers can check progress against the agreement sooner.

Want the handover clause explained for one of these?

Send us the project. We will point you to the clause and the date so you can take it to your lawyer.

Common questions

How long can a developer take to hand over my condo?

Under the standard Schedule H, vacant possession is due within 36 calendar months of the agreement for strata property, and within 24 months under Schedule G for landed property. The date that binds is in your own agreement, so check it with your lawyer.

Can I get compensation if my developer is late?

The standard schedules provide LAD of 10% a year of the purchase price, counted daily from the deadline until you take possession. Whether it applies to you, and how much, is a legal question for your lawyer. This is not legal advice.

What is the TTPR limit and filing deadline?

The Act caps each Tribunal claim at RM50,000 (section 16M as amended) and requires filing within 12 months of the CCC, the end of the defects liability period or termination (section 16N(2)). Confirm the current rules with KPKT or your lawyer.

Has the Housing Development Act changed recently?

We found no enacted change to those figures. KPKT says it is amending Act 118 and drafting the RPDA to replace it, which was at the final drafting stage in Jul 2026. We have not seen it passed.

Talk to us

Comparing new launches and want the completion date explained? We will show you where the date sits in the agreement.

Sources: Laws of Malaysia portal, Attorney General’s Chambers (Act 118 and the 1989 Regulations); Housing Development (Control and Licensing) Regulations 1989 as amended, with 2007 amendments; Act A1289 (2007); Act A1415 (2012); Act 118, 2006 reprint; Bernama, 31 Jul 2026; New Straits Times, 21 Nov 2025; EdgeProp, 3 Aug 2026 (RPDA status); EdgeProp, 22 May 2023 (Federal Court on the Tribunal limit); iProperty guide to claiming LAD and Tay and Partners (the 24 and 36 month periods and the 10% LAD rate, as press and law-firm summaries describe them). General information, not legal advice. Ask your lawyer. Cover photo: Cytonn Photography, Unsplash.

Satu respons kepada “Pemaju Lewat Serah Rumah di Malaysia: Hak LAD dan Tuntutan Tribunal”

  1. […] LAD stands for liquidated ascertained damages. It is a rate fixed in the agreement for late delivery. The standard Schedule G agreement (landed homes) gives the developer 24 months from the agreement date to deliver vacant possession (clause 24(1)). The Schedule H agreement (strata homes) gives 36 months (clause 25(1)). If the developer is late, it pays 10% a year of the purchase price, counted daily from the end of that period until vacant possession (MahWengKwai & Associates, 5 Oct 2020). The older Schedule H text, also reproduced by the National House Buyers Association, says the same. For a worked example and the handover steps, see our guide on developer late delivery. […]